Is it possible to define a custom view that uses a specific sort order whenever it’s invoked?
Thanks,
Dan
I don’t believe this is possible. Tip: remove Summary headers (Format / Show/Hide / Summary Tasks) for a complete Sort of all tasks.
Yes it is possible.
Apply your sort criteria and then save a copy of your current view (lets say you name it “Sorted View”).
Anytime you select this “Sorted View”, the sort criteria will be applied.