Loading...
Quick Links

Import Dependencies from another projects

Home Forums Discussion Import Dependencies from another projects

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #412222 Reply

    I need to import dependencies from another version of the schedule to another version where we have fixed the hierarchy etc.

    Is there an easier/efficient way to ensure accurately importing? Other than using excel…

    #412239 Reply
    Jigs Gaton
    Member
    • Author
    • Forum Pro

    Koushal, if the structure is the same (i.e. Task Name column), have u tried just cutting and pasting the contents of the Predecessors column?

    #412253 Reply

    They are not the same ..I’m trying to import tasks from a working plan to a master sheet.

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: Reply #412253 in Import Dependencies from another projects
Your information:




4 + 4 =