In Project 2010 decimals in Total Slack ?

Home Forums Discussion In Project 2010 decimals in Total Slack ?

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #4983 Reply
    CommunityCommunity
    Keymaster
    Why do decimals numbers appear in total slack after I change a duration from 5 days to 5ed? I did have a baseline set.
    #6382 Reply
    CommunityCommunity
    Keymaster
    This is due to the hours part of the scheduled taks (start / end date and TIME).
    In order to check this, you should change the date format in MS Project to also display the hours & minutes.
    #6396 Reply
    CommunityCommunity
    Keymaster
    I don’t want to see this field in decimal form. Is there a way to stop this.
    #6404 Reply
    CommunityCommunity
    Keymaster
    No. Only costs can have decimal places changed (options). However, you can create a formula in a custom field to provide a duplication of the field.