In PWA 2013, where are microsoft project files stored if no site is configured?

Home Forums Discussion In PWA 2013, where are microsoft project files stored if no site is configured?

Tagged: 

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #485216 Reply
    david.andrew.smith
    Participant

    In PWA 2013, where are the microsoft project files stored if no site is configured? I’m a SharePoint Admin migrating PWA 2010 to PWA 2013. The users created 4 projects back in 2015 but never configured sites for each project. When i click on the Documents button in the ribbon for a project, it says ‘No site configured’. We can open the projects just fine in Project Professional 2013 but the file path only says //myOrg/PWA. I cannot find the mpp files in Site Contents either. Any help would be appreciated.

    #485457 Reply
    Dale Howard
    Member

    David — In Project Server 2013, all of the enterprise projects are stored in the Project Server database in SQL Server. They are NOT stored in SharePoint. Hope this helps.