Loading...
Quick Links

Inactivate task – Query

Home Forums Discussion Inactivate task – Query

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #5217 Reply
    CommunityCommunity
    Keymaster

    Hi,

    I have a task which is in progress (% Complete) is tracked. Now, due to some reasons the same is dropped. How to inactivite such task without making the % complete as zero

    Thanks & regards,

    Venu

    #6922 Reply
    CommunityCommunity
    Keymaster

    You have two options:1. Remove remaining work or otherwise make the task 100% complete (which you don’t want to do)2. Change % complete back to 0 and then inactivate the task (that unfortunately changes work values and removes the indication that work was performed on the task)The normal preferred method is option 1 but either way will work.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Inactivate task – Query
Your information: