Loading...
Quick Links

Inactive Tasks in P2010

Home Forums Discussion Inactive Tasks in P2010

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #5138 Reply
    CommunityCommunity
    Keymaster

    When making tasks inactive, is the related cost excluded from the overall project cost as well? Also, are these inactive tasks still retrievable in previous saved baselines?

     

    Thanks

    #6819 Reply
    CommunityCommunity
    Keymaster

    Hi Angelique,

    Welcome to this Microsoft Project forum:)

    I don’t have Project Server or Professional, so I can’t give you a direct answer.  But why don’t you create a new file, add a few task and costs and try it out to see what happens,

    FAQs, companion products and other useful Project information can be seen at this web address:  http://project.mvps.org/faqs.htm

    Hope this helps – please let us know how you get on 🙂

    Mike Glen
    MS Project MVP (97-11)
    See http://tinyurl.com/2xbhc for my free Project Tutorials

     

    #6820 Reply
    CommunityCommunity
    Keymaster
    • Yes, the cost of inactive tasks is excluded from the overall cost.
    • Yes, if you inactivate the task After the the Baseline has been set. If you set a baseline after you Inactivate the task, then Baseline for those inactive tasks is NOT saved.
Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: Inactive Tasks in P2010
Your information: