    When making tasks inactive, is the related cost excluded from the overall project cost as well? Also, are these inactive tasks still retrievable in previous saved baselines?

     

    Thanks

    #6819 Reply
    Community
    Keymaster

    Hi Angelique,

    Welcome to this Microsoft Project forum:)

    I don’t have Project Server or Professional, so I can’t give you a direct answer.  But why don’t you create a new file, add a few task and costs and try it out to see what happens,

    FAQs, companion products and other useful Project information can be seen at this web address:  http://project.mvps.org/faqs.htm

    Hope this helps – please let us know how you get on 🙂

    Mike Glen
    MS Project MVP (97-11)
    See http://tinyurl.com/2xbhc for my free Project Tutorials

     

    #6820 Reply
    Community
    Keymaster
    • Yes, the cost of inactive tasks is excluded from the overall cost.
    • Yes, if you inactivate the task After the the Baseline has been set. If you set a baseline after you Inactivate the task, then Baseline for those inactive tasks is NOT saved.