Inactive Tasks in P2010

Home Forums Discussion Forum Inactive Tasks in P2010

Viewing 2 reply threads
  • Author
    Posts
    • #5138
      Jay Robinson
      Keymaster

      When making tasks inactive, is the related cost excluded from the overall project cost as well? Also, are these inactive tasks still retrievable in previous saved baselines?

       

      Thanks

    • #6819
      Jay Robinson
      Keymaster

      Hi Angelique,

      Welcome to this Microsoft Project forum:)

      I don’t have Project Server or Professional, so I can’t give you a direct answer.  But why don’t you create a new file, add a few task and costs and try it out to see what happens,

      FAQs, companion products and other useful Project information can be seen at this web address:  https://project.mvps.org/faqs.htm

      Hope this helps – please let us know how you get on 🙂

      Mike Glen
      MS Project MVP (97-11)
      See https://tinyurl.com/2xbhc for my free Project Tutorials

       

    • #6820
      Jay Robinson
      Keymaster
      • Yes, the cost of inactive tasks is excluded from the overall cost.
      • Yes, if you inactivate the task After the the Baseline has been set. If you set a baseline after you Inactivate the task, then Baseline for those inactive tasks is NOT saved.
Viewing 2 reply threads