Loading...
Quick Links

Insert Subprojects, Project 2016

Home Forums Discussion Insert Subprojects, Project 2016

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #412306 Reply

    I have a master project withe 100 activities/tasks with a milestone task of conclusion.

    Later i insert a small subproject (5 tasks)

    I would like to have dependencies between the last tak of my master project and my subproject summary task.

    Then if i track the tasks of master project will have automatically inpact on the subproject inserted.

    Other way How can i constraint (start and finish) the subproject with the master project?

    #412518 Reply
    Josh Logan
    Guest

    Carlos –

    Insert the sub-project, then create the dependency links between the master project’s tasks and the sub-project’s tasks

    Ideally, maintain the sub-project as linked, to the master project (make updates to the linked version of the sub-project); otherwise, the links may go away if you delete/re-add a modified sub-project.

    To create the link:

    1) Select the predecessor task
    2) Hold the CTRL key
    3) Select the successor task and release the CTRL key
    4) Press the “link the selected tasks button” key (Ctrl + F2) in the Task Menu.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Insert Subprojects, Project 2016
Your information:




79 − = 74