      Dear all,
      could you please help me on below subject.

      I have created a consolidated plan inserted three external plans. All three external plans have different working week (5, 6, 7 days).
      The overall plan I created has the default working week (5 days) but paradoxically the two subproject with 6 and 7 working days maintain their initial duration, start, and finish dates.

      It seems to me that the issue is only visual, although the Gantt Chart shows two days non working days per week it calculates the initially programed working days for each subproject separately. Am I correct? Have you faced such an issue?

      Thank you in advance for your help.

      Best regards

      Stergios Kokkkoris