Home Forums Discussion Inserting Task/Milestone as predecessor into middle of a task

This topic contains 1 reply, has 2 voices, and was last updated by Larry Christofaro Larry Christofaro 4 months ago.

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #415825 Reply

    MSP newbie

    I’m fairly new to the Project and I was wondering if there is way to insert a task or milestone as predecessor into middle of a certain task?
    I don’t think splitting a task is an answer…

    #415829 Reply
    Larry Christofaro
    Larry Christofaro
    Participant
    • Expert
    • Forum Pro
    • Ombud

    Newbie but not a newbie question. Project provides a couple of solutions. You can adjust when the successor task starts by using either a number of days or a percent.
    Task 1 with a negative lag of 3 days: 1FS-2 days
    Task 1 at 50% of task 1 duration: 1FS-50%
    Hope that helps…:-)

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Inserting Task/Milestone as predecessor into middle of a task
Your information:




34 + = 36