    Hi MSP Experts,
    I am curious why we are not able to see Last Published Date in the backend of MSP reporting. We can see the field in PWA but not in reporting. We monitor this to ensure planners are publishing their projects a regular basis to ensure the data is reportable. We recently saw an example where Last Modified Date < Last Published Date and this stumped me. Normally the Last Modified Date would also be updated when a user Publishes. Perhaps they simply published but didn’t make any changes to the project?
    Thoughts from others on how we can monitor this across projects in PWA via a reportable solution please. Thanks