Linking both start and finish dates

Home Forums Discussion Linking both start and finish dates

Tagged: ,

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #413530 Reply
    Chris Hax
    Member

    Hello,

    Cleaning Room 1
    – Step one (A)
    – Step two (B)
    – Meets Cleanliness Standards (C) [Gline #FF]
    Clearance Testing (D)
    – Wipe Samples (E)
    – Air Sampling (F)
    – Passes Clearance Testing (G)

    I would like to link tasks such that:
    – C completes when G completes (link C to G line number with FF after it I think)
    – A & B complete when C completes
    – but their start dates are not adjusted by the links
    – and the duration (days) adjust to reflect the start and finish dates
    I tried linking the completion of A & B with completion of C but it adjusts the start date to match the days for those tasks even though the days are listed as “days?”.

    Any direction would be greatly appreciated.
    Regards,

    Chris

    #413533 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Sorry Chris, hard to follow the issue. If you are wanting the system to adjust the duration based on predecessors / successors, Project doesn’t do that. Project will only move the task. If that’s not the case, please provide additional details.

    #413534 Reply
    Chris Hax
    Member

    Thank you for the response Larry.

    I would like to link Task B so that the following occurs:
    Task B to Start when Task A completes
    Task B to Finish when Task C completes

    If I have to manually adjust the days I can live with that but at least the dates will be correct.

    Regards,

    Chris

    #413535 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    As you probably know by now it won’t work. A task start date is determined by the predecessor that causes the latest start date.

Viewing 4 posts - 1 through 4 (of 4 total)