I created a consolidated projects files by grouping three projects.
Ex: I created a start to finish link between tasks of 2 projects. Link is there but the successor task stays were I was. In other words the finish date one task in project 1 will become the star date of another task in project 2.
I was expecting that start date of project 2 would change based on the link a made.
What should I do so that start date of project 2 following link a made.
Links between projects affect successor tasks only, not the project itself. You need to go to Project Information to set the project start date. Hope that helps…