Locking Tasks

Home Forums Discussion Forum Locking Tasks

Viewing 1 reply thread
  • Author
    Posts
    • #474941
      Reggie Brown
      Guest

      I need to be able to lock certain tasks to prevent users from editing them because they are used to rollup into reports. I set the locked flag to “yes” on these tasks, yet I am still able to edit them. I’m using Project 2016 desktop version.

    • #474973
      Sai Prasad
      Participant

      Locked flag is used for Project Online / Server to prevent team members from entering additional time on a completed task. Though there are alternatives available like macros, customizing filters and views, it will not prevent users from not editing the tasks.

Viewing 1 reply thread
  • You must be logged in to reply to this topic.