Hi all,
I have a question regrading the resources.
1.0 How do I assign salary staff irrepect of work load with fixed salary per month?
2.0 if he/she works only 25% for first 3 month and then after 50% for rest of the year, how do I adjust the salary 25% from project for 3 month & remaining month, if he/she had salary of USD 1800 per month?
P.S I am new in new here.
Hi Suman, welcome to the forum. Best way to think through the problem is to figure out the requirement. Reading your question you could create a monthly task and either use the Fixed Cost task column or create a cost resource. It doesn’t sound like a great solution but works which is key. Hope that helps…
hi Larry,
I really appreciate for responding to my post. Very kind of you. I will come back again when need. Thank you.