Loading...
Quick Links

Microsoft Project 2013

Home Forums Discussion Microsoft Project 2013

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #418049 Reply
    Suman Dahal
    Participant

    Hi all,

    I have a question regrading the resources.
    1.0 How do I assign salary staff irrepect of work load with fixed salary per month?
    2.0 if he/she works only 25% for first 3 month and then after 50% for rest of the year, how do I adjust the salary 25% from project for 3 month & remaining month, if he/she had salary of USD 1800 per month?

    P.S I am new in new here.

    #418084 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Hi Suman, welcome to the forum. Best way to think through the problem is to figure out the requirement. Reading your question you could create a monthly task and either use the Fixed Cost task column or create a cost resource. It doesn’t sound like a great solution but works which is key. Hope that helps…

    #418126 Reply
    Suman Dahal
    Participant

    hi Larry,

    I really appreciate for responding to my post. Very kind of you. I will come back again when need. Thank you.

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: Microsoft Project 2013
Your information:




33 − = 29