  • #413469 Reply
    Elnur
    Guest

    Can you please explain why task time slips 1 hour to previous date when I try to print timeline?

    #413470 Reply
    Sai Prasad
    Participant
    • Community Leader
    • Forum Pro

    Can you a screenshot of the timeline to look at?

    #413471 Reply
    Elnur
    Guest

    I have uploaded pictures in below Email.

    https://upload.run/veoejx
    https://upload.run/gviyme

    #413474 Reply
    Sai Prasad
    Participant
    • Community Leader
    • Forum Pro

    Thanks for sharing it across. I recreated the exact plan here and did not notice any differences between Timeline view and Print Preview. In your image, I noticed the two tasks are manually scheduled (Task mode). What is the start time of these tasks?