MS Project 2013 Critical Task Text Formatting

Home Forums Discussion Forum MS Project 2013 Critical Task Text Formatting

  • This topic has 3 replies, 3 voices, and was last updated 7 years ago by Sonja S..
Viewing 2 reply threads
  • Author
    Posts
    • #366442

      I use format text styles to set critical task text as red. When the task is completed, it is no longer on the critical path and the text should turn back to the conventional black font. Sometimes the text turns black, other times it does not. Is this a bug or is there another reason? Thanks in advance for your insight.

    • #367516
      Sai Prasad
      Participant

      Mike – I am not able to reproduce the issue. I followed the same steps in Project Professional 2013 – changed the text style of critical tasks, marked a critical task completed, the color changed to black (the default color). Do you mean to say for some tasks the color changes and for some tasks it works correctly? Also, try clearing the formatting that might have been set on some these tasks by first selecting all the tasks, then click Task ribbon, in the Editing group click Clear .. Clear Formatting. This action will ensure any font color changed on that tasks will be cleared and the text style font color will be applied.

      • #409408
        Sonja S.
        Guest

        I had the same problem and clearing the formatting on the task also worked for me. Thank you so much.

    • #367591

      Sai, clearing the formatting worked. The template were working from had some unknown formatting issues, but not anymore! Thanks very much. Mike

Viewing 2 reply threads
  • You must be logged in to reply to this topic.