MS project 2013 query

Home Forums Discussion MS project 2013 query

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #413751 Reply
    angeline
    Guest

    Hi forum,

    I work with MSProject 2013 and I am looking for a solution with regard to the following:
    I have a team of 3 people who are assigned to projects in multiple countries. The standard coordination time is set at 4 months duration and is no more than 32 hours e.g. 8 hours a month.

    If I include a 4 month window in MS Project then MSP will generate a day or 8 hours with a total of days for 4 months while I only need it to be 32 hours that need to be allocated – 8 hours a month. Each project member will have multiple countries allocated in line with above duration time.

    Can anyone let me know how I can set this up in MS Project?

    #413755 Reply
    Larry Christofaro
    Participant

    Angeline, try this. Enter the task with the proper task duration. Then make sure you enter the hours when you assign the resource. You can’t do this directly assigning the resource in the task sheet, but:
    Use the Assign resources dialog box and enter 32h in the Units column
    Use the split screen on a task or Gantt chart with the Task Form, and enter 32 in the work column with the resource
    Use the Task Information box and enter 32h in the Units column

    You will want to make sure that the Effort Driven flag is set to No, which you can’t do on a Fixed Work task type. I suggest Fixed Units but Fixed Duration also works.

    Hope that helps…good luck