Home Forums Discussion MS Project 2016. Real progress of the project, % complete

This topic contains 2 replies, has 2 voices, and was last updated by Larry Christofaro Larry Christofaro 2 weeks, 4 days ago.

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #416724 Reply

    Sasha

    Hello! Is there a formula or some way to calculate the real progress of the project in %? Unfortunately, there are no resources, no money, no time spent, only tasks with their duration, start, finish, baseline and % completion. Tried through the formula of the planned % completion:

    Round(IIf([Milestone],IIf([Start]>=[Status Date],0,100),IIf([Start]>=[Status Date],0,IIf(ProjDateDiff([Finish],[Status Date],[Project Calendar])>0,100,ProjDateDiff([Start],[Status Date],[Project Calendar])/[Duration]*100)))) & “%”

    But it does not reflect reality, it is simply tied to the status date, and if we increase the % of completion as, for example, ahead of the plan, the indicator does not change. We also tried another method, created 2 numerical fields, one assigned the values of the formula IIf([% Complete]=100,1,0), the second one – IIf([Milestone],0,1) then calculated by formula: IIf([Summary],Format([Number1]/[Number2],”###%”),” “) , but still the calculations are not quite accurate, besides, with the increase in the percentage of completion tasks, the formula calculates 104% for some tasks. Are there other methods for calculating the real progress of the project? Thank you!

    #416726 Reply

    robert oler

    I would think that in the absence of the data you mentioned (hours, cost, etc.) the %WorkComplete field would suffice, no?

    #416728 Reply
    Larry Christofaro
    Larry Christofaro
    Participant
    • Expert
    • Forum Pro
    • Ombud

    Sasha, sorry I don’t have an answer for you that corrects your formula. have you tried just using the Physical % Complete field and manually updating your tasks…or maybe using that as an override for situations where you calculation doesn’t work (if Physical % complete exists, use that, else…)?

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: MS Project 2016. Real progress of the project, % complete
Your information:




4 + 4 =