MS Project Pro 2019 — Start and Finish Variance results are incorrect

Home Forums Discussion Forum MS Project Pro 2019 — Start and Finish Variance results are incorrect

Viewing 0 reply threads
  • Author
    Posts
    • #415751
      Chaz
      Guest

      I get these incorrect variances in line 1 below. I’ve added a new “Test” task and it calculates correctly.

      Baseline Start Start Start Variance Baseline Finish Finish Finish Variance
      Line 1 GO-LIVE Release 1 11/8/19 11/19/19 30 days 11/10/19 11/21/19 30 days
      Line 2 Test Go-Live Task 11/8/19 11/21/19 7 days 11/10/19 11/21/19 7 days

      Has anyone seen something like this?