MS Project Pro 2019 — Start and Finish Variance results are incorrect

Home Forums Discussion MS Project Pro 2019 — Start and Finish Variance results are incorrect

Viewing 1 post (of 1 total)
  • Author
    Posts
  • #415751 Reply
    Chaz
    Guest

    I get these incorrect variances in line 1 below. I’ve added a new “Test” task and it calculates correctly.

    Baseline Start Start Start Variance Baseline Finish Finish Finish Variance
    Line 1 GO-LIVE Release 1 11/8/19 11/19/19 30 days 11/10/19 11/21/19 30 days
    Line 2 Test Go-Live Task 11/8/19 11/21/19 7 days 11/10/19 11/21/19 7 days

    Has anyone seen something like this?