  • #88846 Reply
    Rosemary
    Participant

    Is there a Best Practice to track and follow estimated Planned Start Dates in tasks? We are using “TBD-01/31/2014” in the Planned Start field when a customer is not sure when the task is to begin, but the PM must put the task in the schedule.
    Are there any issues with doing it the “TBD-01/31/2014” way?
    Is there another way to track these estimated dates (putting the info in the comments & notes fields is not enough)?