Home › Forums › Discussion Forum › MS Project Server 2013 compatibility with Project Standard
I know that MS Project Pro is required to interactively work with MS Project Server 2013, however I would like to know how compatible MS Project Standard is with the Sharepoint/server. Are all of our copies of MS Project Standard obsolete if we go over to the MS Project 2013 Server? Or is there still some functionality there? I can’t find anything online. Any articles just assume that it will be used with Professional, not the Standard.
Hello Mark,
Project Standard will not Sync with SharePoint. All copies of Project Standard will be obsolete, ie you need Project Pro to open/save projects to Project Server. Sorry to be the bringer of bad news.