MS Project – Total Project Duration and Activity Sequencing

Home Forums Discussion Forum MS Project – Total Project Duration and Activity Sequencing

Viewing 1 reply thread
  • Author
    Posts
    • #413875
      Thilini
      Guest

      I am using MS Project Professional 2016

      When I enter the total project duration column ( customer field ) in to my project plan, it calculated total time duration for the tasks without taking activity sequencing into consideration. For an example, Activity 1 is taking 9 Days and Activity 2 and Activity 3 will take 4 days each, but here Activity 2 and Activity 3 has start to start sequence. When it comes to total duration is shows 17 days. But it ideally should be 13 days. Please provide your support on this.

    • #413877
      Abdul Rahman Mohammed
      Guest

      Hi,
      Based on the description of the plan, the total duration comes to 13 days, and if excluded 4 days of weekend that it comes to 9 working days. That seems to be pretty small and straight sequence of activities.
      Probably you may have to reset your calendar to a standard one and try again.