Loading...
Quick Links

Multiple Task Dependency Type Selection

Home Forums Discussion Multiple Task Dependency Type Selection

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #2150 Reply
    CommunityCommunity
    Keymaster

    How do you set all tasks dependency types to Fixed Duration?

    #6540 Reply
    CommunityCommunity
    Keymaster

    You are confusing task typing and dependency relationships.

    Relationships are finish-to-start which says that when one task is completed, the next task will start

    Task type of fixed duration means that there is a set duration for a task.  (double click on a task, advanced tab to change)

    One has nothing to do with the other.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Multiple Task Dependency Type Selection
Your information: