My Work task update

Home Forums Discussion Forum My Work task update

Tagged: ,

Viewing 5 reply threads
  • Author
    Posts
    • #5293
      Preeti Dimble
      Keymaster

      I am trying to use the “My Work” function to update tasks assigned to me,  the page groups the tasks it shows tasks for a current period, and tasks at a future period… anyone know how to remove the “Planning Window – periods of time”?

    • #7037
      Preeti Dimble
      Keymaster

      Hi, if this is 2010 then click on the Group By field, and choose None instead of the planning Window.

    • #7042
      Preeti Dimble
      Keymaster

      Thanks Ben!

       

      Do you know where to find/edit/change the Approval Manager for project? I’ve been trying to get up to speed on the My Work Tasks/Approval Center, and having a little trouble? Thanks

    • #7043
      Preeti Dimble
      Keymaster

      Yes, the approval manager is known as the status manager.

      Regards,  Ben.

    • #7078
      Preeti Dimble
      Keymaster

      Ben,

      I was looking at your article on Automatically Approve Task Status Updates.” Once the task has been approved, and the % Complete is updated in the schedule, I notice that the individual schedule still needs to be published for all the updated items to be pushed through. Is there any auto way to publish, rather than to open up every schedule to do so??

       

      Thanks

      Also, I am looking for a on-line MSP Training program and I have seen the one offered by MS Project Experts, do you have any you would recommend?

    • #7079
      Preeti Dimble
      Keymaster

      Joe, this is available out of the box in Project Server 2010, but not in 2007.  There are a few third party tools that can provide this for you if you are using 2007, or you can program yourself.  I assume a search will give you options.  I know of a couple but haven’t used them so prefer not to make a recommendation.

Viewing 5 reply threads
  • You must be logged in to reply to this topic.