Loading...
Quick Links

My Work task update

Home Forums Discussion My Work task update

Tagged: ,

Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • #5293 Reply
    CommunityCommunity
    Keymaster

    I am trying to use the “My Work” function to update tasks assigned to me,  the page groups the tasks it shows tasks for a current period, and tasks at a future period… anyone know how to remove the “Planning Window – periods of time”?

    #7037 Reply
    CommunityCommunity
    Keymaster

    Hi, if this is 2010 then click on the Group By field, and choose None instead of the planning Window.

    #7042 Reply
    CommunityCommunity
    Keymaster

    Thanks Ben!

     

    Do you know where to find/edit/change the Approval Manager for project? I’ve been trying to get up to speed on the My Work Tasks/Approval Center, and having a little trouble? Thanks

    #7043 Reply
    CommunityCommunity
    Keymaster

    Yes, the approval manager is known as the status manager.

    Regards,  Ben.

    #7078 Reply
    CommunityCommunity
    Keymaster

    Ben,

    I was looking at your article on Automatically Approve Task Status Updates.” Once the task has been approved, and the % Complete is updated in the schedule, I notice that the individual schedule still needs to be published for all the updated items to be pushed through. Is there any auto way to publish, rather than to open up every schedule to do so??

     

    Thanks

    Also, I am looking for a on-line MSP Training program and I have seen the one offered by MS Project Experts, do you have any you would recommend?

    #7079 Reply
    CommunityCommunity
    Keymaster

    Joe, this is available out of the box in Project Server 2010, but not in 2007.  There are a few third party tools that can provide this for you if you are using 2007, or you can program yourself.  I assume a search will give you options.  I know of a couple but haven’t used them so prefer not to make a recommendation.

Viewing 6 posts - 1 through 6 (of 6 total)
Reply To: My Work task update
Your information:




15 − = 12