I have a team that is overseas and has different working days than we do (S-TH).
I created a sub-project that calculated everything just as I wanted and it immediately stopped working correctly when I linked it into the Master with the standard calendar.
Does anyone know how to accomodate this? I’m using project server 2010 and am not allowed to have task or resource level calendars.