Notify team members that prereqs for their tasks are complete?

Home Forums Discussion Forum Notify team members that prereqs for their tasks are complete?

Viewing 5 reply threads
  • Author
    Posts
    • #413564
      Scott Milner
      Guest

      Hello MPUG!

      I’m a relatively new Project user, and manage IT projects in a large corporate environment. We use Project Server and Project 2016 clients for our project managers, and our development teams utilize PWA licenses to receive and update their project tasks.

      Most of our projects consist of 1000-2000 tasks and utilize 20 – 40 developers from various departments. Our standard process is to release (via a publish tag) tasks to the project teams a week in advance, and the teams try to update the task status as they work through them to keep the project status current.

      One bit of frustration that our teams have is that we really don’t have a process for notification that the predecessor (prerequisite task) task for their work has been completed. We rely on phone calls, emails, chat window, etc. for this back-channel communication, which can be cumbersome.

      The question that comes up is, “Isn’t there a way for Project to notify the owner of a task that the predecessor for that task is complete, and that they can begin work?” The concept that they are looking for comes from Atlassian’s Jira, which we use for issue tracking and maintenance/change request items. I’m told a Jira item can be created and ‘passed’ from one developer to another, and Jira notifies the next resource via email that they can begin their work.

      One way that I can think of (with our existing setup) is to only release tasks that can be worked on immediately (rather than the 1 week increments that we use today). I could then manually release the next tasks as the predecessor task for it is complete. However, this is incredibly ‘hands on’ from a PM perspective, and would require all project team members update PWA immediately upon completing their work. I would also have to be accepting project updates from PWA on a very regular basis (it’s a manual process at this point)… in short, it would be pretty cumbersome.

      Does anyone have any ideas on how we might be able to notify our team members via project that a prerequisite task has been closed?

      Thanks!

      Scott

    • #413565
      Scott Milner
      Guest

      Sorry… we release tasks PWA via a publish flag not tag… I didn’t catch the typo until after I submitted!

      sm

    • #413577
      Larry Christofaro
      Participant

      Sorry, nothing out of the box. Maybe someone can think of a work-around.

    • #413579
      Sai Prasad
      Participant

      I agree with Larry, but you have close to solution using Manage My Resources’ Alerts and Reminders in PWA. Check this article https://support.office.com/en-us/article/get-email-reminders-about-your-work-in-project-web-app-2372c181-1c98-416a-9306-ac28f027334b#bkmk_managerteam. It describes how a project manager can decide which notifications your team needs.

    • #413614

      I’ve written a VB script that tags each task based on whether the task is “ready to start” or “is underway”. You should be able to update this and send an email based on the “ready to start” tag. I execute the script weekly as I update my projects. I use MSP 2016 desktop Professional. No on-line and no server. I’d be happy to share…

      Mark

    • #413615

      Option Explicit

      Sub CheckPreds()

      ‘ This application cycles through a project and:
      ‘ Places data in the tasks Text15 to indicate the status of the task as done, underway or ready to start
      ‘ changes the font for the row to gray if the task is complete or if the task is inactive
      ‘ changes the font for the row to red if the task is on the critical path and is not complete or inactive

      ‘ Written by Mark Darby
      ‘ Updated on 8 May 2018

      Dim proj As Project
      Dim ts As Tasks ‘Active task selection
      Dim tsk As Task
      Dim tPred As Task

      Dim tskCtr, ctr As Integer

      Dim tskCount As Integer ‘ Count of the number of tasks in the project
      Dim pCount As Integer ‘ Counts the number of predecessor tasks for any given task
      Dim perComp As Double ‘ Percentage Complete for any given task
      Dim pCompl As Integer ‘ Counts the number of complete tasks for any given task

      Dim Ready As Boolean ‘ Flags the task as being ready to execute

      Set proj = ActiveProject

      OutlineShowAllTasks

      FilterApply “All Tasks”

      tskCount = ActiveProject.Tasks.Count

      Debug.Print “Beginning Formatting Loop”

      For tskCtr = 1 To tskCount

      Set tsk = proj.Tasks(tskCtr)
      SelectRow Row:=tskCtr, RowRelative:=False, Height:=0, Add:=False
      Font Color:=pjBlack, Bold:=False
      Font32Ex StrikeThrough:=False

      If Not tsk.Active Then
      Font Color:=pjGray, Bold:=False
      Font32Ex StrikeThrough:=True
      Else
      If tsk.PercentComplete = “100” Then
      Font Color:=pjGray, Bold:=False
      Font32Ex StrikeThrough:=False
      ‘Else
      ‘ If tsk.Critical Then
      ‘ Font Color:=pjRed, Bold:=True
      ‘ Font32Ex StrikeThrough:=False
      ‘ End If ‘tsk.Cricital
      End If ‘tsk.PercentageComplete = “100”
      If tsk.Summary Then
      Font Bold:=True
      End If
      End If ‘Not tsk.Active

      Next tskCtr

      Debug.Print “Beginning Task Statusing Loop”

      For tskCtr = 1 To tskCount

      Set tsk = proj.Tasks(tskCtr)
      tsk.Text15 = “–”

      If tsk Is Nothing Then
      ‘ do nothing on blank lines
      Else
      If tsk.Active Then
      If Not tsk.PercentComplete = “100” Then
      If Not tsk.Summary Then
      If tsk.ActualStart <> “NA” Then
      tsk.Text15 = “Underway”
      Else
      pCount = 0 ‘ total count
      pCompl = 0 ‘ complete countFor Each tPred In tsk.PredecessorTasks
      For Each tPred In tsk.PredecessorTasks
      pCount = pCount + 1
      If tPred.PercentComplete = “100” Then
      pCompl = pCompl + 1
      End If
      Next tPred
      If pCount = pCompl Then
      tsk.Text15 = “Ready”
      End If ‘PCount = pCompl
      End If ‘tsk.ActualStart <> “NA”
      End If ‘Not tsk.summary
      End If ‘Not tsk.PercentComplete = “100”
      Else
      tsk.Text15 = “–”
      End If ‘not tsk.active
      End If ‘T is nothing

      Next tskCtr

      SelectTaskField Row:=1, Column:=”Name”, RowRelative:=False

      Beep

      End Sub

      ——————————–
      BTW — I welcome any feedback on this….

Viewing 5 reply threads
  • You must be logged in to reply to this topic.