    Hi

    I am setting oData connection from MSPOL to Power BI the “clasic way”

    mydomain.sharepoint.com/sites/pwa/_api/Projectdata

    this gives 41 tables, but my question, if I want to add a field “missing” in the data model

    for exmaple taksk – field successors

    can I do this ? : add some more fields with oData connexion on top of standard date model

    regards

    #412869 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Unfortunately you cannot add project fields to the connection. You can only create calculated fields.