Process Completed ===== [6/22/2011 10:41 AM] Failed to build the OLAP cubes. Error: Invalid call to GetJoinForCustomFieldDimension. Cannot join “Task Non Timephased” fact with a custom field of entity Assignment
I am unalbe to build the OLAP cubes due to the above listed error, this is a new problem and I am not sure if it is related the previous issue that I am having with resources.
I did an administrative back up of my custom fields, then did an administrative restore of the custom fields, rebuilt the OLAP cubes and now everything seems to be working.