  • #380746 Reply
    kamlesh Parmessur
    Participant

    Hello everybody

    What should be the options/setting to properly use the stop and resume fields in Ms project 2013.
    sometimes when update a task which has not progress as per plan, i split the task(reschedule incomplete part of task to start in the future); and the resume date column automatically updates itself to a date which is too far in the future.

    #380748 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Kamlesh, it’s hard to tell what is happening but the resume date would be set for previously in-process tasks with remaining work, out to either the date specified in the update project or to a date constrained by predessessor tasks with remaining work. You might check to see if there are predessessors on those tasks and if that might be your problem. Otherwise please provide additional information. Hope that helps…