Outline numbers in task groups

Home Forums Discussion Forum Outline numbers in task groups

Viewing 3 reply threads
  • Author
    Posts
    • #111400
      David Foss
      Member

      How do I remove the outline #’s that precede titles in my task groups?s
      example:
      Group by Product (Text1)
      1.1.1 Product Group A
      task 1
      task 2
      1.1.2 Product Group B
      task 3
      task 4

    • #111405
      Jack Fox
      Guest

      There is a checkbox on the Format menu that says Outline, uncheck that box. 2010 / 13

    • #111410
      David Foss
      Member

      already unchecked…
      Project Pro 2013

    • #111411
      David Foss
      Member

      outline # only shows with ‘Maintain Hierarchy’ is checked, and I need that…

Viewing 3 reply threads