Output schedule for those without Project?

Home Forums Discussion Output schedule for those without Project?

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #481947 Reply
    cbass1224
    Participant

    Hello, all.

    Is there a way to output an entire Gantt chart view to excel? I’ve found articles about exporting data, but I’d like to get the whole thing. We need to be able to share with outside companies and groups that don’t use Project.

    #483392 Reply
    Student
    Guest

    Hello,

    i was looking for something similar, i found a macro thats able to produce an exact copy of the Gantt chart.

    https://github.com/PopovGP/Export-MS-Project-to-MS-Excel

    i hope this helps you!

    #483443 Reply
    online12
    Participant

    100% Pass Rate Guaranteed PMP certificate without exam in Saudi Arabia Buypmpwithoutexams@yahoo.com | Buy TEF certificate without exam Saudi Arabia | Buy PMP certificate without exam in Saudi Arabia

    https://www.buypmpwithoutexams.com can help you obtain Certifications for every stage of your career.

    PMP Certification Training Course in Saudi Arabia
    PMP Certification in Saudi Arabia is a great start for the professionals to acquire and get certified in PMP. There are a lot of changes in the PMP course topics in the latest 6th edition of the PMP certification course. If you are an aspiring project manager or looking for PMP online training certification in project management, then the PMP course in Saudi Arabia is the right choice to celebrate the success of project management in your career. PMP Training in Saudi

    #483984 Reply
    bobc455
    Member

    Are you looking to export the Gantt Chart? Or just the data?

    Data is relatively easy but the chart itself would probably need to be a screen shot of some kind.

    Thanks!

    -Bob C.

    #483987 Reply
    welshjs
    Participant

    What I would do is print the GANTT chart but choose PDF as the format. If you’re careful with the settings you can get the whole thing to show up. You can drag and drop that into an email and maybe even an excel.

    If you want the task list and the chart part as something you can view and edit in Excel that’s another story.

Viewing 5 posts - 1 through 5 (of 5 total)