    How do I show overtime on the Gantt?  The task with the overtime only shows regular working times – it is the predecessor to another task.  The linked task starts after the working times and not after the overtime which is not shown on the Gantt.
    #6373 Reply
    CommunityCommunity
    Keymaster
    Overtime is a funny thing in Project. It’s basically extra hours done in addition to standard working time. Entering Overtime reduces the duration so it won’t show seperately on the Gantt chart.
    #6386 Reply
    CommunityCommunity
    Keymaster
    Overtime can have many meanings. Let’s assume that we mean overtime the extra hours a resource will work during a certain period compared to a standard working day.
    This involves the calendar option, where the standard day for a resource is extended; e.g. with a working slot from 18:00 tot 23:00.
    When doing this the activity will take place during the extended day-hours. In order to show this in the gantt-chart you have to change the timescale on the Gantt-chart view to display the hours.