Loading...
Quick Links

Planned Administrative Time – MSP Server 2010

Home Forums Discussion Planned Administrative Time – MSP Server 2010

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #5034 Reply
    Community
    Keymaster

    How do you report planned administrative time in Project Server 2010?  Back in EPM2007, we used a “Plan Administrative Time” menu selection, but I don’t see that anymore.  Am I missing something simple that’s in plain sight?

    #6589 Reply
    Community
    Keymaster

    Its slightly different from 2007…Here are the steps.

    • Click on Timesheet link from Quick Launch on the left.
    • Go to the timesheet period that you want to plan administrative time Time for by clicking on select period.
    • Make sure that Planned line is displayed. If not, Insert the Planned” line by checking the box on the ribbon
    • Input hours on the Planned line for the administrative time that you are planning.
    • Select the task by clicking on checkbox beside the name of the task
    • Click on  Send Status >>  Selected Tasks.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Planned Administrative Time – MSP Server 2010
Your information:




82 − = 77