Loading...
Quick Links

Postive actual costs are being summarized as negative

Home Forums Discussion Postive actual costs are being summarized as negative

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #5286 Reply
    CommunityCommunity
    Keymaster

    I have a resource loaded activity that has positive actual amounts entered, but the summary bar shows a negative actual cost.  This task is 100%.  What are some things I should investigate?

    thank you!

    #7027 Reply
    CommunityCommunity
    Keymaster

    sorry…failed to mention, this is Project Pro 2010 (we utilize PWA as well).

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Postive actual costs are being summarized as negative
Your information:




76 − = 73