Printing a Tracking Gantt View (Project 2010)

Home Forums Discussion Printing a Tracking Gantt View (Project 2010)

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #219502 Reply
    Michael DeMarie
    Participant

    It seems that when printing from Project 2010 the Tracking Gantt view does not print, rather the Gantt chart prints without the baseline bars. Is it possible to print (actually plot to a large-format plotter) the Gantt chart with the baseline bars?

    #220652 Reply
    J Fox
    Guest

    Did you look at Format/Format/Bar Styles? it’s different for each view.

    #220701 Reply
    Michael DeMarie
    Participant

    J Fox – You are a genius! I used the Gantt Chart Wizard while in the Tracking Gantt view, added the baseline bars and all prints perfectly.

    Thanks!