Home › Forums › Discussion Forum › Printing a Tracking Gantt View (Project 2010)
Tagged: baseline bars, printing, Tracking Gantt
It seems that when printing from Project 2010 the Tracking Gantt view does not print, rather the Gantt chart prints without the baseline bars. Is it possible to print (actually plot to a large-format plotter) the Gantt chart with the baseline bars?
Did you look at Format/Format/Bar Styles? it’s different for each view.
J Fox – You are a genius! I used the Gantt Chart Wizard while in the Tracking Gantt view, added the baseline bars and all prints perfectly.
Thanks!