Problem Modifying Row Height in Tracking Gantt view table

Home Forums Discussion Problem Modifying Row Height in Tracking Gantt view table

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #4948 Reply
    CommunityCommunity
    Keymaster
    In the attached file, I have been trying to adjust the row height in the Tracking Gantt chart view to be smaller, like it is in the Gantt Chart view.  I have not been successful in making this happen.  Any suggestions anyone?
    I am using MS Project 2007 Professional.
    #6291 Reply
    CommunityCommunity
    Keymaster
    Regina, I have found that the bar type text, when added to the top or bottom of the bar, causes the overall row height to expand. I think you have a number of text fields selected to be placed on the top of the bar.
    #10006 Reply
    CommunityCommunity
    Keymaster
    Hello –
    Row height cannot less the height of the bars displayed. Choose Format, Barstyles and in Text tab, remove/reorder the fields displayed.
    Hope this helps
    — Sai, MCTS Project
Viewing 3 posts - 1 through 3 (of 3 total)