    If you are using Project Server, how do the project managers track and report progress on tasks assigned to resources?

    #29738 Reply
    Jill Baird
    Participant

    The resources usually reports their own progress in PWA.  Starting with MSP 2010, if a resource doesn’t have access to a computer (maybe a resource on a construction site), another person can be set to always report progress for them, using the “Default Assignment Owner” feature.  If another person needs to report status for a person on just a few tasks, you can set an individual assignment’s “Assignment Owner” field in the Task Usage view.