Home › Forums › Discussion › Project 2010
Tagged: Gantt Chart view, Microsoft Project 2010
I am using Project 2010, frequently in my gantt chart view some summary tasks would freeze and would not expand any more. I can go to another view such as a tracking gantt or create a new view and that will function normally. Any suggestions??
Hi GM,
Have you installed SP1 and the latest updates?
FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm
Mike Glen
MS Project MVP (97-11)
See http://tinyurl.com/2xbhc for my free Project Tutorials
“
Are you using manual scheduled tasks? Manual scheduled tasks will not calculate summary values. If you don’t have the SP1 patch, get it as Mike as suggested.