Project 2010 Crash when using Autofilter – bug?

Home Forums Discussion Project 2010 Crash when using Autofilter – bug?

Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • #334696 Reply

    I have discovered a situation which causes MS Project to crash and I’m wondering if it’s a known issue. If I filter on Finish, then change the finish of a resulting task, Project crashes. Every time. Is it my installation of Project or is it a known issue with 2010?

    Matt McCarty, PMP

    #334699 Reply
    Larry Christofaro
    Participant

    I did a quick test and was able to change the finish date of a filtered task. Of course a simple test doesn’t prove anything. Have you tried it as a simple test outside of a structured project and does it happen then as well? There really isn’t a formal list of bugs that Microsoft publishes (that would be too revealing).

    #334700 Reply

    PS: It happens whether or not the file is saved locally. It only appears to happen with the Finish field. Start and %Complete seem to work normally. I created a small sample file and it still happened.

    #334725 Reply
    Larry Christofaro
    Participant

    Hmm, then one of two things are probably happening. Either I’m still doing something different than you (I’m using the auto-filter for one) or you don’t have an update that fixes the issue. Of course there is always that third option of unexplained reasons…:-( If you really want to figure this out, itemize the exact steps you are taking and send me or post a picture of the exact WBS of a sample plan. Thanks…

    #334833 Reply

    Thanks Larry,
    I found, downloaded and installed the most recent update and it appears to have fixed the problem! I should’ve thought of that. Good lookin’ out.

    Matt

    #334835 Reply
    Larry Christofaro
    Participant

    Glad it solved the problem…