Project 2016: How to factor in overhead costs per resource?

Home Forums Discussion Forum Project 2016: How to factor in overhead costs per resource?

Viewing 2 reply threads
  • Author
    Posts
    • #412736
      sabina
      Guest

      I’m trying to factor in overhead costs to each resource (insurance, vacation time, etc). It seems like the only place to do this is in the per use cost, however I have multiple tasks assigned to each resource every week so it seems the per use cost would be calculated higher than what the actual overhead cost is.

      Should I be looking to add this cost in somewhere else?

    • #412744
      Larry Christofaro
      Participant

      Sabrina, the best way to incorporate overhead costs is to apply it to the hourly rate. That way the overhead applied to the project is related to the hours worked. Hope that helps…

    • #412792
      Sabina
      Guest

      Thanks Larry!

Viewing 2 reply threads
  • You must be logged in to reply to this topic.