Have recently upgraded from a previous version of Project to 2013. When I quit working with the previous version and saved my work, the file would open to where I left off when I wanted to resume work. 2013 does not do that; it opens at task 1 and I have to scroll down to where I was last working. Can someone please tell me how to make 2013 open to where the last work was done?
Thanks
Edwin, interesting question. I’ve never read or heard of this before so I did some of my own testing. Unfortunately I’m getting the same results you are. Project 2010 opens the project where I left off and 2013 opens at task 1. I do not have an answer other than it’s a change (or bug) with 2013.