Project Owner for one particular project gets changed often?

Home Forums Discussion Project Owner for one particular project gets changed often?

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #403439 Reply
    Vignesh Gopinathlal
    Guest

    Project owner of one particular project gets changed often to other person (Who is not a resource on that project).

    #403447 Reply

    What version of Project ex: 2013 standalone, 2013 server, 2016, project 365?

    I’m running 2013 server and the only ways I know of that the OWNER can be changed are
    1) the current owner changes it via the PDP page in PWA
    2) another resource with Admin security levels changes it in the PDP
    3) it is possible an external interface is accessing the project DB and changes it, using an API of some type

    General questions that may help others diagnose
    Is it always the same name that it is changed to? or Random names?
    What is the frequency of changes? Randomly throughout the day? Once a week on Friday night?
    Are there any batch or API type processes that run at the same time/frequency as the changes occur?

    #403705 Reply
    Vignesh Gopinathlal
    Guest

    Hi,

    Thanks Daryl.

    We user 2013 server. Owner gets changed to one person all the time who has admin rights. It changes when the original PM of the plan edit and publishes the plan. Frequency is some thing once in a week.

    Thanks,
    Vignesh Gopinathlal

    #403794 Reply

    I’ve done some checking on my end since we’re running 2013 also and this is not an issue we are running into. Sorry I can’t offer any other thoughts