Home › Forums › Discussion Forum › Project Randomly Changes Project Owner
We are on project server 2010. We are experiencing a case where the project owner is randomly changed to another user who has been given permissions to update the project. We know that these users are not changing it themselves in PWA, but somehow it switches after the user has been updating the project. Anyone have any insight?
I do not have the answer, however, once a project has gone live I would propose that only one person be allowed to update the schedule file directly. This is not to say to avoid the ability to allow status to be made via the Server, is to maintain good configuration control over the project file itself. Consider yourself fortunate not to have the file corrupted by multiple updating it; specifically not knowing if they just do things that might cause corruption.