Project Server 2010 – Customize Task display in PWA when drill into Project schedule details

Home Forums Discussion Project Server 2010 – Customize Task display in PWA when drill into Project schedule details

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #4903 Reply
    Community
    Keymaster
    Hi there:
    Anyone knows how to customize task view to display in PWA when viewing project schedule?.  Here is our use case:
    1) We have a project where tasks are divided into 2 teams (I.E Designer and Programmer)
    2) We want to create a view in PWA to color code the tasks based by team (i.e. Designer’s task in Orange and Programmer’s task in Light Yellow)
    The goal is to achieve a clear overview for the users when viewing the project via PWA and able to identify the tasks more efficiently.
    Sincerely, Joseph C. Yin
    Qualcomm Incorporated.
    #6171 Reply
    Community
    Keymaster
    No Sorry, Joe. No way as far as I know.
    What you could do is use the resource team field to sort or have a custom filed with task type and sort/filter/group on that field to diferentuate.
    The other option (bit of a cludge) run up a SRSS report that was coloured in the fashion you want and display in the RS viewer Webpart in the PWA.
    Sorry no better news mate.
    Simon Newton
Viewing 2 posts - 1 through 2 (of 2 total)