Loading...
Quick Links

Project Server 2010 – Project Web App Home Page – Approval Count is wrong

Home Forums Discussion Project Server 2010 – Project Web App Home Page – Approval Count is wrong

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #30971 Reply

    On my Project Web App home page it shows that I have 39 tasks pending my approval, when in fact I have none.  I’ve searched google to come up with a fix but no success to date.  Has anyone had this same problem?  How did you fix it?

    #31273 Reply
    Tom Herrington
    Participant

    Check the status manager setting in the projects, using project professional, that are appearing in your Approval Center.  When a resource submits from a timesheet it is the status manager that receives the update for approval.  If it should be someone else, change it.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Project Server 2010 – Project Web App Home Page – Approval Count is wrong
Your information:




− 1 = 1