Loading...
Quick Links

Project Server 2010 PWA Task Update Best Practice?

Home Forums Discussion Project Server 2010 PWA Task Update Best Practice?

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #50659 Reply
    Charlie Yi
    Participant

    Can anyone suggest a best method of tracking task progress via PWA?  In MS Project, you would expect task owners or project manager to enter the following:

    Actual Start, Actual Finish, Actual Duration or Work, Remaining Duration or Work, and then “update” all un-started/finished work after the Status Date.

    Is it possible to use the same update process using PWA?  I noticed that some fields mentioned above are greyed-out (can’t enter data) in PWA.

    Any guidance will be much appreciated.

     

    #365111 Reply
    Matt
    Guest

    I’m having the same problem. Need users to be able to update Actual Start and Actual Finish from PWA but it’s not possible it seems. any help would be appreciated!!!

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Project Server 2010 PWA Task Update Best Practice?
Your information:




7 + 3 =