Can anyone suggest a best method of tracking task progress via PWA? In MS Project, you would expect task owners or project manager to enter the following:
Actual Start, Actual Finish, Actual Duration or Work, Remaining Duration or Work, and then “update” all un-started/finished work after the Status Date.
Is it possible to use the same update process using PWA? I noticed that some fields mentioned above are greyed-out (can’t enter data) in PWA.
Any guidance will be much appreciated.
I’m having the same problem. Need users to be able to update Actual Start and Actual Finish from PWA but it’s not possible it seems. any help would be appreciated!!!